Density Test Report

Date :02/18/2026
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :02/18/2026 15:00
Onsite Hours :01:15
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :Sunny
Departure Time :02/18/2026 16:15
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/18/2026 1 20.8 100.2 2026-010 98.1 22.4 102.1 98 D6938 Pass
Location : SSMH S-1 to S-2, Elv/Depth :3 to 4 feet over pipeline
Comment : Gauge Serial No. :77-19952
02/18/2026 2 19.3 100.9 2026-010 98.1 22.4 102.9 98 D6938 Pass
Location : SSMH S-1 to S-2, Elv/Depth :3 to 4 feet over pipeline
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, February 18, 2026
Reviewer Name / DateKenneth Mosman, February 26, 2026