Density Test Report

Date :02/23/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :02/23/2026 08:00
Onsite Hours :9:30
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :02/23/2026 17:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/23/2026 1 27.7 94.0 2025-023 SP 103.5 18.9 90.8 95 D6938 Fail
Location : Lot #40, Elv/Depth :1029
Comment : In-situ moisture contents way above optimum moisture content. Recommend scarify and aerate prior to recompaction. Gauge Serial No. :91487
02/23/2026 2 19 98.8 2025-022 SP 103.7 16.1 95.3 95 D6938 Pass
Location : Lot #40, Elv/Depth :1029.4
Comment : Gauge Serial No. :91487
02/23/2026 3 22.3 99.9 2025-023 SP 103.5 18.9 96.5 95 D6938 Pass
Location : Lot #40, Elv/Depth :1028.9
Comment : Gauge Serial No. :91487
02/23/2026 4 20.4 101.2 2025-023 SP 103.5 18.9 97.8 95 D6938 Pass
Location : Lot #40, Elv/Depth :1029
Comment : Gauge Serial No. :91487
02/23/2026 5 18.3 88.6 2025-022 SP 103.7 16.1 85.4 95 D6938 Fail
Location : Lot #39, Elv/Depth :1023
Comment : Recommend thinning lift thickness and recompaction. Gauge Serial No. :91487
02/23/2026 6 21.5 98.7 2025-023 SP 103.5 18.9 95.4 95 D6938 Pass
Location : Lot #39, Elv/Depth :119.9
Comment : Gauge Serial No. :91487
02/23/2026 7 21.4 119.7 2025-023 SP 103.5 18.9 95.3 95 D6938 Pass
Location : Lot #39, Elv/Depth :1023.90
Comment : Gauge Serial No. :91487
02/23/2026 8 19.7 117.9 2025-023 SP 103.5 18.9 95.2 95 D6938 Pass
Location : Lot #39, Elv/Depth :1025.48
Comment : Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, February 23, 2026
Reviewer Name / DateKenneth Mosman, February 26, 2026