Density Test Report

Date :02/23/2026
Project No :2025C211
Client Company :Pulte
Arrival Time :02/23/2026 07:00
Onsite Hours :07:00
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :02/23/2026 14:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/23/2026 1 19.8 84.4 FP 2 100.0 18.5 84.4 95 D6938 Fail
Location : Retaining wall #2, Elv/Depth :7 baskets
Comment : contractor will compact, and will be retested Gauge Serial No. :77-19952
02/23/2026 2 (retest) 14.7 101.1 FP 2 100.0 18.5 101.1 95 D6938 Pass
Location : Retaining wall #2, Elv/Depth :7 baskets
Comment : Gauge Serial No. :77-19952
02/23/2026 3 16.3 95.3 FP 2 100.0 18.5 95.3 95 D6938 Pass
Location : Retaining wall #2, Elv/Depth :7 baskets
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, February 23, 2026
Reviewer Name / DateKenneth Mosman, March 03, 2026