Daily Field Report

Date :02/25/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :02/25/2026 08:00
Onsite Hours :08:00
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :cloudy
Departure Time :02/25/2026 16:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the pipe contractor continue installing 30″ CMP storm line between manholes #B2 and B4. Backfilling for the deep excavations was observed, and compacting efforts appeared to be suitable for job requirements.

The grading contractor continued placing fill for the added slope embankment green area and compacted with a vibratory sheep-foot roller.

The drilling contractor (Advance) continued drilling hard rock at building Lots #47 and 48 using two drill rigs.

The erosion contractor (Valor) was on site and continued grass seeding and placing mat blankets at pond embankment slopes.

The water line contractor continued 8″ DIP installation at Nature Walk Boulevard between manholes #8 and 9.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

30" cmp storm installation and backfill

Backfill and compacting efforts

Matting and grass seeding at pond slope embankment

Drilling holes at lot# 47

Fill placement and compacting at lot# 66