Density Test Report

Date :02/26/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :02/26/2026 08:00
Onsite Hours :05:30
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :rainey
Departure Time :02/26/2026 13:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
02/26/2026 1 15.3 95.6 Field proctor #6 98.0 17.2 97.6 95 D6938 Pass
Location : 30" CMP storm backfill between B2 and B3, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :91643
02/26/2026 2 15.9 96.6 Field proctor #6 98.0 17.2 98.6 95 D6938 Pass
Location : Backfill at 30" CMP storm between B3 and B2, Elv/Depth :2 feet below finished grade
Comment : Gauge Serial No. :91643
02/26/2026 3 14.3 102.2 2025-033 SP 104.0 16.2 98.3 95 D6938 Pass
Location : Backfill at 30" CMP storm between B3 and B4, Elv/Depth :8.5 feet below finished grade
Comment : Gauge Serial No. :91643
02/26/2026 4 14.0 101.7 2025-033 SP 104.0 16.2 97.8 95 D6938 Pass
Location : Backfill at 30" CMP storm between B3 and B4, Elv/Depth :6.5 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, February 26, 2026
Reviewer Name / DateKenneth Mosman, March 03, 2026