Density Test Report

Date :03/19/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :03/19/2026 11:00
Onsite Hours :02:30
Name of the Project :Seven Hills PHASE 13, UNIT 4 Lots
Project Location :Dallas
Weather :sunny
Departure Time :03/19/2026 13:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
03/19/2026 1 21.2 93.6 2025-033 SP 104.0 16.2 90.0 95 D6938 Fail
Location : Building Lots #41 and 42, Elv/Depth :8 feet below finished grade
Comment : Moisture contents well above optimum. Recommend scarify and aerate soils prior to recompaciton. Gauge Serial No. :91643
03/19/2026 2 22.3 93.9 2025-033 SP 104.0 16.2 90.3 95 D6938 Fail
Location : Building lots #41 and 42, Elv/Depth :8 feet below finished grade
Comment : Moisture contents well above optimum. Recommend scarify and aerate soils prior to recompaciton. Gauge Serial No. :91643
03/19/2026 3 21.6 95.1 2025-033 SP 104.0 16.2 91.4 95 D6938 Fail
Location : Building lots # 41 and 42, Elv/Depth :8 feet below finished grade
Comment : Moisture contents well above optimum. Recommend scarify and aerate soils prior to recompaciton. Gauge Serial No. :91643
Technician Signature / DateClyde Smith, March 19, 2026
Reviewer Name / DateKenneth Mosman, March 24, 2026