Concrete Test Report

Date :03/19/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :03/19/2026 06:00
Onsite Hours :06:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :03/19/2026 12:00
ASEC Technician Name :Samara Simha Reddy Kandi

Concrete Placement Information

Location(S): N/A
Testing: 4 Set of concrete specimens (6 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Specimen
Pick Up:
4 Sets of concrete specimens/ 6 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks: Our representative was on site to sample fresh concrete placed in the retaining wall. A total of 4 sets of 6 specimens each were cast.

Field Test Data

Specimen Type Selection : Cylinder

Set Number :A
Date Sampled :03/19/2026
Sampled By :Samara Simha Reddy Kandi
Contractor :N/A
Truck Number :N/A
Time Batched :N/A
Location of Placement :N/A
Number of samples cast :6
Ambient Temperature (°f) :N/A
Slump (in.) :4
Water added (gal.) :N/A
Laboratory Number :2026-061
Time Sampled :N/A
Weather Condition :sunny
Concrete Supplier :N/A
Mix ID :N/A
Quantity of Load (cu. yd.) :N/A
Sample Cast :4
Specified Strength :N/A
Concrete Temperature(°f) :57
Air Content (%) :1.5
Unit Weight (pcf) :N/A

Strength Test Results

Specimen Number Scheduled Test Date Date Tested Age (days) Dia(in.) Area (sq in.) Maximum Loads (lbf) Strength (lbs) % Design Strength Type of Fracture
1 03/26/2026 03/26/2026 7 3.98 12.44 69390 5580 Infinity Type 2
2 03/26/2026 03/26/2026 7 3.98 12.44 74235 5970 Infinity Type 3
3 04/16/2026 N/A
4 04/16/2026 N/A
5 04/16/2026 N/A
6 05/14/2026 N/A

UNLESS OTHERWISE SPECIFIED, TESTS WERE PERFORMED IN ACCORDANCE WITH ASTM TEST METHODS C31, C39, C138, C143, C173, AND C1064. FRACTURE TYPE INDICATED BY NUMBER.

(Type 1) Cone (Type 2) Cone-split (Type 3) Vertical (Type 4) Shear (Type 5) Edge Fracture (Type 6) Pointed

Field Test Data

Specimen Type Selection : Cylinder

Set Number :B
Date Sampled :03/19/2026
Sampled By :Samara Simha Reddy Kandi
Contractor :N/A
Truck Number :N/A
Time Batched :N/A
Location of Placement :N/A
Number of samples cast :6
Ambient Temperature (°f) :N/A
Slump (in.) :4.5
Water added (gal.) :N/A
Laboratory Number :2026-061
Time Sampled :N/A
Weather Condition :sunny
Concrete Supplier :N/A
Mix ID :N/A
Quantity of Load (cu. yd.) :N/A
Sample Cast :4
Specified Strength :N/A
Concrete Temperature(°f) :50
Air Content (%) :1.3
Unit Weight (pcf) :N/A

Strength Test Results

Specimen Number Scheduled Test Date Date Tested Age (days) Dia(in.) Area (sq in.) Maximum Loads (lbf) Strength (lbs) % Design Strength Type of Fracture
1 03/27/2026 03/27/2026 8 3.97 12.38 64716 5230 Infinity Type 5
2 03/26/2026 03/26/2026 7 3.96 12.35 67474 5460 Infinity Type 1
3 04/16/2026 N/A
4 04/16/2026 N/A
5 04/16/2026 N/A
6 05/14/2026 N/A

UNLESS OTHERWISE SPECIFIED, TESTS WERE PERFORMED IN ACCORDANCE WITH ASTM TEST METHODS C31, C39, C138, C143, C173, AND C1064. FRACTURE TYPE INDICATED BY NUMBER.

(Type 1) Cone (Type 2) Cone-split (Type 3) Vertical (Type 4) Shear (Type 5) Edge Fracture (Type 6) Pointed

Field Test Data

Specimen Type Selection : Cylinder

Set Number :C
Date Sampled :03/19/2026
Sampled By :Samara Simha Reddy Kandi
Contractor :N/A
Truck Number :N/A
Time Batched :N/A
Location of Placement :N/A
Number of samples cast :6
Ambient Temperature (°f) :N/A
Slump (in.) :6
Water added (gal.) :N/A
Laboratory Number :2026-061
Time Sampled :N/A
Weather Condition :sunny
Concrete Supplier :N/A
Mix ID :N/A
Quantity of Load (cu. yd.) :N/A
Sample Cast :4
Specified Strength :N/A
Concrete Temperature(°f) :51
Air Content (%) :1.4
Unit Weight (pcf) :N/A

Strength Test Results

Specimen Number Scheduled Test Date Date Tested Age (days) Dia(in.) Area (sq in.) Maximum Loads (lbf) Strength (lbs) % Design Strength Type of Fracture
1 03/26/2026 03/26/2026 7 3.97 12.38 72829 5880 Infinity Type 2
2 03/26/2026 03/26/2026 7 3.96 12.35 71260 5770 Infinity Type 3
3 04/16/2026 N/A
4 04/16/2026 N/A
5 04/16/2026 N/A
6 05/14/2026 N/A

UNLESS OTHERWISE SPECIFIED, TESTS WERE PERFORMED IN ACCORDANCE WITH ASTM TEST METHODS C31, C39, C138, C143, C173, AND C1064. FRACTURE TYPE INDICATED BY NUMBER.

(Type 1) Cone (Type 2) Cone-split (Type 3) Vertical (Type 4) Shear (Type 5) Edge Fracture (Type 6) Pointed

Field Test Data

Specimen Type Selection : Cylinder

Set Number :D
Date Sampled :03/19/2026
Sampled By :Samara Simha Reddy Kandi
Contractor :N/A
Truck Number :N/A
Time Batched :N/A
Location of Placement :N/A
Number of samples cast :6
Ambient Temperature (°f) :N/A
Slump (in.) :5
Water added (gal.) :N/A
Laboratory Number :2026-061
Time Sampled :N/A
Weather Condition :sunny
Concrete Supplier :N/A
Mix ID :N/A
Quantity of Load (cu. yd.) :N/A
Sample Cast :4
Specified Strength :N/A
Concrete Temperature(°f) :54
Air Content (%) :1.3
Unit Weight (pcf) :N/A

Strength Test Results

Specimen Number Scheduled Test Date Date Tested Age (days) Dia(in.) Area (sq in.) Maximum Loads (lbf) Strength (lbs) % Design Strength Type of Fracture
1 03/26/2026 03/26/2026 7 3.97 12.38 77144 6230 Infinity Type 2
2 03/26/2026 03/26/2026 7 3.96 12.35 73070 5920 Infinity Type 2
3 04/16/2026 N/A
4 04/16/2026 N/A
5 04/16/2026 N/A
6 05/14/2026 N/A

UNLESS OTHERWISE SPECIFIED, TESTS WERE PERFORMED IN ACCORDANCE WITH ASTM TEST METHODS C31, C39, C138, C143, C173, AND C1064. FRACTURE TYPE INDICATED BY NUMBER.

(Type 1) Cone (Type 2) Cone-split (Type 3) Vertical (Type 4) Shear (Type 5) Edge Fracture (Type 6) Pointed

Technician Signature / DateSamara Simha Reddy Kandi, March 19, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026