- Home
- Daily Field Report Report ID: 91667
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
On the above date our representative was on site to observe the concrete pour at the north side bridge embankment mud mats for the foundation. The contractor placed a total of 116 cubic yards of 3000 psi concrete for a total of eight strip footings numbered 1, 2, 4, 5, 6, 7 and 8. See attached sketch. Our representative assisted in molding three sets of (5) test cylinders for compression strength testing. Concrete index testing (air content, unit weight and slump tests along with air and mix temperature checks) was performed. The concrete sampling and results will be in a separate report. The footings not poured were number 3, 9, 10 and 11. A concrete pump truck was used for placement.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Concrete batch ticket

Pouring footings using pump truck

Concrete testing

Poured mat mats

Pouring mud mat

Poured mud mats

Sketch of poured mud mat footings.
