Density Test Report

Date :04/03/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :04/03/2026 08:00
Onsite Hours :07:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :04/03/2026 15:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/03/2026 1 19.2 100.1 2025-023 SP 103.5 18.9 96.7 95 D6938 Pass
Location : Lot #22, Elv/Depth :1041.5
Comment : Gauge Serial No. :91487
04/03/2026 2 15.4 104.2 2025-023 SP 103.5 18.9 100.7 95 D6938 Pass
Location : Lot #22, Elv/Depth :1041
Comment : Gauge Serial No. :91487
04/03/2026 3 15.9 107.2 2025-023 SP 103.5 18.9 103.6 95 D6938 Pass
Location : Lot #46, Elv/Depth :1028
Comment : Gauge Serial No. :91487
04/03/2026 4 24.2 122.2 2025-023 SP 103.5 18.9 95.1 95 D6938 Pass
Location : Lot #46, Elv/Depth :1028.5
Comment : Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, April 3, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026