Daily Field Report

Date :04/02/2026
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :04/02/2026 07:00
Onsite Hours :01:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :Sunny
Departure Time :04/02/2026 08:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.

Our ASEC representative was on site to observe the contractor (Lewis Contracting) and for the observation/testing of the placement of fill/backfill.

The contractor continued to place soil lifts approximately 12 inches in thickness across the water main that runs under main street into the site and around the grease traps. The lifts appeared to be compacted with a trench roller and a vibrating smooth drum roller. Density testing was performed, and test results were provided to the contractor. The contractor is starting to haul stockpiled topsoil off the site.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSean Willett, April 2, 2026
Reviewer Name / DateKenneth Mosman, April 08, 2026