Density Test Report

Date :04/09/2026
Project No :2025C149
Client Company :Davidson Homes
Arrival Time :04/09/2026 07:30
Onsite Hours :10:00
Name of the Project :Grove at E. Thompson Mill Rd
Project Location :Buford
Weather :sunny
Departure Time :04/09/2026 17:30
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/09/2026 1 16.3 100.3 2025-023 SP 103.5 18.9 96.9 95 D6938 Pass
Location : Lot #64, Elv/Depth :1030
Comment : Reworked on lots Gauge Serial No. :91487
04/09/2026 2 20.5 118.9 2025-023 SP 103.5 18.9 95.4 95 D6938 Pass
Location : Lot #64, Elv/Depth :1030
Comment : Gauge Serial No. :91487
04/09/2026 3 22.7 120.8 2025-023 SP 103.5 18.9 95.2 95 D6938 Pass
Location : Lot #63, Elv/Depth :1028
Comment : Gauge Serial No. :914487
04/09/2026 4 22.9 98.5 2025-023 SP 103.5 18.9 95.2 95 D6938 Pass
Location : Lot #63, Elv/Depth :1026
Comment : Gauge Serial No. :91487
04/09/2026 5 18 103.4 2025-023 SP 103.5 18.9 99.9 95 D6938 Pass
Location : Lot #64, Elv/Depth :1032
Comment : Gauge Serial No. :91487
04/09/2026 6 16.9 102.7 2025-023 SP 103.5 18.9 99.2 95 D6938 Pass
Location : Lot #63, Elv/Depth :1031
Comment : Gauge Serial No. :91487
Technician Signature / DateSamara Simha Reddy Kandi, April 9, 2026
Reviewer Name / DateKenneth Mosman, April 13, 2026