Daily Field Report

Date :04/10/2026
Project No :2025C216
Client Company :Artisan
Arrival Time :04/10/2026 07:30
Onsite Hours :05:00
Name of the Project :NW (Lots) Unit 4 PH 1A & 1B
Project Location :Dallas
Weather :Sunny
Departure Time :04/10/2026 12:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the paving contractor continue subbase preparation for Nature Walk Parkway between sanitary sewer manholes # 9 and 6 (fine grading and compacting).

The pipe contractor continued installing 24″ CMP at storm line C for Unit 4, Phase 2.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

24" cmp storm line installation at C line

Subbase prep. at Nature Walk Pkwy.

Technician Signature / DateClyde Smith, April 10, 2026
Reviewer Name / DateKenneth Mosman, April 14, 2026