Daily Field Report

Date :04/14/2026
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :04/14/2026 02:00
Onsite Hours :01:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :Sunny
Departure Time :04/14/2026 03:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.

Our ASEC representative was on site to observe the contractor (Lewis Contracting) and for the observation/testing of the placement of fill/backfill. The contractor began to place soil lifts in the excavated topsoil area. Lifts were spread with a dozer and compacted with a vibrating smooth drum roller. Density testing was performed and test results were provided to the contractor.

The contractors have begun pouring curbs.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

fill area

curbs

curbs

Technician Signature / DateSean Willett, April 14, 2026