Skip to content

Daily Field Report

Date :04/24/2026
Project No :2025C146
Client Company :Davidson Homes, LLC
Arrival Time :04/24/2026 09:00
Onsite Hours :01:00
Name of the Project :Greene Farms Subdivision
Project Location :1451 Highway 113, Cartersville, Georgia
Weather :Sunny
Departure Time :04/24/2026 10:00
ASEC Technician Name :Sean Willett

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.

Our ASEC representative was on site as requested by the contractor for the observation/testing of the placement of fill/backfill. The contractor is backfilling the roadway patches with lifts of GAB. Lift size is approximately 1 foot thick and compacted using a jumping jack and trench roller. The GAB appears to be well compacted. The contractor has a water barrel onsite to add water to the GAB as needed.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSean Willett, April 24, 2026
Reviewer Name / DateKenneth Mosman, April 27, 2026