Density Test Report

Date :04/20/2026
Project No :2025C211
Client Company :Pulte
Arrival Time :04/20/2026 07:00
Onsite Hours :05:00
Name of the Project :Haley's Bluff - Philadelphia Rd.
Project Location :Jasper
Weather :Sunny
Departure Time :04/20/2026 12:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
04/20/2026 1 16.5 106.4 2025-055 107.3 15.5 99.2 95 D6938 Pass
Location : Lot #33, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
04/20/2026 2 23.1 92.6 FP 2 100.0 18.5 92.6 95 D6938 Fail
Location : Lot #34, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
04/20/2026 3 26.1 90.8 FP 2 100.0 18.5 90.8 95 D6938 Fail
Location : Lot #35, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
04/20/2026 4 15.7 97.9 FP 2 100.0 18.5 97.9 95 D6938 Pass
Location : Lot #36, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, April 20, 2026
Reviewer Name / DateKenneth Mosman, April 27, 2026