Density Test Report

Date :05/01/2026
Project No :2026C103
Client Company :Artisan
Arrival Time :05/01/2026 11:00
Onsite Hours :04:00
Name of the Project :NW PH 2, UNIT 4
Project Location :Dallas
Weather :Sunny
Departure Time :05/01/2026 15:00
ASEC Technician Name :Sean Willett

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
05/01/2026 1 15.0 96.6 Field proctor #6 98.0 17.2 98.6 95 D6938 Pass
Location : B-13, Elv/Depth :3 to 2 feet below finished grade
Comment : Gauge Serial No. :77-19952
05/01/2026 2 14.4 96.2 Field proctor #6 98.0 17.2 98.2 95 D6938 Pass
Location : B-13, Elv/Depth :3 to 2 feet below finished grade
Comment : Gauge Serial No. :77-19952
05/01/2026 3 15.2 95.1 Field proctor #6 98.0 17.2 97.0 95 D6938 Pass
Location : B-13, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
05/01/2026 4 12.1 96.4 Field proctor #6 98.0 17.2 98.4 95 D6938 Pass
Location : B-13, Elv/Depth :at finished grade
Comment : Gauge Serial No. :77-19952
Technician Signature / DateSean Willett, May 1, 2026
Reviewer Name / DateKenneth Mosman, May 05, 2026