Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
The crew continued installing DIP pipe by excavating the trench and leveling the subgrade to prepare a stable base for the pipe installation. After the trench was graded, the new DIP section was aligned and joined to the existing DIP line. Once the pipe connection was completed, the crew placed a lift of suitable backfill material above the pipe and compacted.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.