- Concrete Test Report Report ID: 95372
- Edit Download Report
Concrete Test Report
Date :06/17/2026
Project No :2026C133
Client Company :Artisan
Arrival Time :06/17/2026 9:00
Onsite Hours :-8:00
Name of the Project :Salacoa (AKA Boone Ford Rd) Robert's Dam
Project Location :Calhoun
Weather :clear and sunny
Departure Time :06/17/2026 1:00
ASEC Technician Name :Narayana Ganesh Undavalli
Concrete Placement Information
Location(S):
N/A
Testing:
1 Set of concrete specimens (6 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:
Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)
Deviations and/or noncompliances were noted during the field placement (refer to remarks below)
Specimen
Pick Up: 1 Sets of concrete specimens/ 6 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Pick Up: 1 Sets of concrete specimens/ 6 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing:
Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks:
concrete Temperature = 88
Ambient Temperature = 78
Slump = 3.5
Air = 2.3
unit wt of concrete = 143.
Technician Signature / DateNarayana Ganesh Undavalli, June 17, 2026