Concrete Test Report

Date :06/17/2026
Project No :2026C133
Client Company :Artisan
Arrival Time :06/17/2026 9:00
Onsite Hours :-8:00
Name of the Project :Salacoa (AKA Boone Ford Rd) Robert's Dam
Project Location :Calhoun
Weather :clear and sunny
Departure Time :06/17/2026 1:00
ASEC Technician Name :Narayana Ganesh Undavalli

Concrete Placement Information

Location(S): N/A
Testing: 1 Set of concrete specimens (6 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Specimen
Pick Up:
1 Sets of concrete specimens/ 6 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks: concrete Temperature = 88 Ambient Temperature = 78 Slump = 3.5 Air = 2.3 unit wt of concrete = 143.
Technician Signature / DateNarayana Ganesh Undavalli, June 17, 2026