Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
The crew continued installing the water line along Road C. The area was excavated to the required depth, the subgrade was leveled, and approximately 120 lineal feet of 8-inch DIP was installed in the northeast direction. After installation, backfill material was placed and compacted using a trench compactor and sheep-foot roller.