Concrete Test Report

Date :07/07/2026
Project No :2026C122
Client Company :WSP
Arrival Time :07/07/2026 9:00
Onsite Hours :03:00
Name of the Project :Courtesy Pkwy Expansion
Project Location :Conyers
Weather :clear and sunny
Departure Time :07/07/2026 12::0
ASEC Technician Name :Narayana Ganesh Undavalli

Concrete Placement Information

Location(S): N/A
Testing: 1 Set of concrete specimens (2 per set) were cast during the cast-in-place concrete pour at the above referenced location, in accordance with ASTM C31. The specimen will remain on site for the initial 24-48 hrs curing.
Compliance:

Field placement of concrete appeared to be in accordance with the project specifications (i.e., slump, temperature, etc) (refer to remarks below)

Deviations and/or noncompliances were noted during the field placement (refer to remarks below)

Specimen
Pick Up:
1 Sets of concrete specimens/ 2 specimen per set were picked up & transported to AS Engineering and Consulting LLC (ASEC) for curing and testing in accordance with ASTM C39, C670/1231
Field Curing: Specimen were stored for the initial 24 hours.
Near the poured structure
In an insulated curing box
Other
Remarks: Test 1 Temp of concrete = 88 Amb temp = 81 Slump = 4 air = 4 unit wt of concrete = 145.
Technician Signature / DateNarayana Ganesh Undavalli, July 7, 2026