Density Test Report

Date :07/07/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :07/07/2026 14:00
Onsite Hours :03:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :sunny
Departure Time :07/07/2026 17:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
07/07/2026 1 20.1 105.2 2025-036 SP 107.0 18.5 98.3 98 D6938 Pass
Location : Lot #28, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
07/07/2026 2 19.4 105.4 2025-036 SP 107.0 18.5 98.5 98 D6938 Pass
Location : Lot #28, Elv/Depth :at finished grade
Comment : Gauge Serial No. :38069
07/07/2026 3 17.4 99.4 2025-033 SP 104.0 16.2 95.6 95 D6938 Pass
Location : Lot #29, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :38069
07/07/2026 4 17.8 98.1 2025-033 SP 104.0 16.2 94.3 95 D6938 Fail
Location : Lot #29, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :38069
07/07/2026 5 16.3 101.6 2025-033 SP 104.0 16.2 97.7 95 D6938 Pass
Location : Lot #29, Elv/Depth :4 feet below finished grade
Comment : Retest of Test #4 after recompaction. Gauge Serial No. :38069
Technician Signature / DateSamara Simha Reddy Kandi, July 7, 2026
Reviewer Name / DateKenneth Mosman, July 30, 2026