Density Test Report

Date :08/14/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :08/14/2026
Onsite Hours :
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :sunny
Departure Time :08/14/2026
ASEC Technician Name :Russell Hendrix

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/14/2026 1 19.0 83.6 2025-032 SP 94.9 25.0 88.1 90 D6938 Fail
Location : North side 10 feet from wall, Elv/Depth :-3 feet below grade
Comment : recommended removal of wet soil. Gauge Serial No. :92204
Technician Signature / DateRussell Hendrix, August 14, 2026