Density Test Report

Date :08/17/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :08/17/2026
Onsite Hours :
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :sunny
Departure Time :08/17/2026
ASEC Technician Name :Russell Hendrix

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/17/2026 1 14.6 99.2 2025-033 SP 104.0 16.2 95.4 95 D6938 Pass
Location : 20 feet from wall, North side, Elv/Depth :-1 foot below elevated sewer line
Comment : Gauge Serial No. :92204
08/17/2026 2 11.2 103.5 2025-033 SP 104.0 16.2 99.5 95 D6938 Pass
Location : 5 feet south of previous test, 18 feet from wall, Elv/Depth :-1 foot below elevated sewer line
Comment : Gauge Serial No. :92204
08/17/2026 3 14.1 101.2 2025-033 SP 104.0 16.2 97.3 95 D6938 Pass
Location : 20 feet south of last test, 15 feet from wall, Elv/Depth :-1 foot below elevated sewer line
Comment : Gauge Serial No. :92204
08/17/2026 4 15.5 102.3 2025-033 SP 104.0 16.2 98.4 95 D6938 Pass
Location : 10 feet from wall, south end, Elv/Depth :-1 foot below elevated sewer line
Comment : Gauge Serial No. :92204
Technician Signature / DateRussell Hendrix, August 17, 2026
Reviewer Name / DateKenneth Mosman, August 18, 2026