- Daily Field Report Report ID: 97003
- Edit Download Report
Daily Field Report
Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials
submittals. The following observations were observed on site this day.
LOCATION: TAXIWAY-GOLF TOWARDS NORTH-EAST DIRECTION
The crew proceeded with excavation activities at the Taxiway golf site, removing soil to a depth of 36 inches from ground level in preparation for the construction of a concrete structure that will incorporate a drainage pipe. Prior to commencing the excavation, the area was checked and found to meet project specifications.
To facilitate the removal of the excavated soils, a tandem dump truck was employed. After the excavation was completed, the soil in the designated area was compacted using a trench packer. The work was performed in the northeastern section of the site.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.