- Density Test Report Report ID: 97064
- Edit Download Report
Density Test Report
Date :08/21/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :08/21/2026 11:30
Onsite Hours :03:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :sunny
Departure Time :08/21/2026 14:30
ASEC Technician Name :Clyde Smith
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 08/21/2026 | 1 | 22.4 | 90.9 | 2025-032 SP | 94.9 | 25.0 | 95.8 | 95 | D6938 | Pass |
| Location : | Roadway between B6.1-DWCB and B4-STJB, Elv/Depth :-10' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 08/21/2026 | 2 | 22.9 | 91.4 | 2025-032 SP | 94.9 | 25.0 | 96.3 | 95 | D6938 | Pass |
| Location : | same as 1, Elv/Depth :-10' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 08/21/2026 | 3 | 13.9 | 100.3 | 2025-033 SP | 104.0 | 16.2 | 96.4 | 95 | D6938 | Pass |
| Location : | same as 1, Elv/Depth :-10' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 08/21/2026 | 4 | 14.2 | 99.2 | 2025-033 SP | 104.0 | 16.2 | 95.4 | 95 | D6938 | Pass |
| Location : | Same as 1, Elv/Depth :-10' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 08/21/2026 | 5 | 15.1 | 101.0 | 2025-035 SP | 107.8 | 13.0 | 93.7 | 95 | D6938 | Fail |
| Location : | Embankment slope at bridge abutment between S.S. manholes #3 and 2, Elv/Depth :-4' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 08/21/2026 | 6 | 16.4 | 101.2 | 2025-035 SP | 107.8 | 13.0 | 93.9 | 95 | D6938 | Fail |
| Location : | Same as # 5, Elv/Depth :-4' | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
Technician Signature / DateClyde Smith, August 21, 2026