Density Test Report

Date :08/26/2026
Project No :2026C101
Client Company :Artisan
Arrival Time :08/26/2026 07:30
Onsite Hours :08:00
Name of the Project :Seven Hills PHASE 13, UNIT 3 Lots
Project Location :Dallas
Weather :sunny
Departure Time :08/26/2026 15:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
08/26/2026 1 13.3 102.3 2025-033 SP 104.0 16.2 98.4 95 D6938 Pass
Location : Fill placement at roadway between B6.2 ST G1, B6 ST JB and B4-ST JB, Elv/Depth :8 feet below finished grade
Comment : Gauge Serial No. :91643
08/26/2026 2 12.7 102.1 2025-033 SP 104.0 16.2 98.2 95 D6938 Pass
Location : Fill placement at roadway between B6.2 ST G1, B6 ST JB and B4-ST JB, Elv/Depth :7 feet below finished grade
Comment : Gauge Serial No. :91643
08/26/2026 3 18.1 123.0 2025-035 SP 107.8 13.0 96.6 95 D6938 Pass
Location : Fill placement at roadway between B6.2 ST G1, B6 ST JB and B4-ST JB, Elv/Depth :6 feet below finished grade
Comment : Gauge Serial No. :91643
08/26/2026 4 17.8 103.3 2025-035 SP 107.8 13.0 95.8 95 D6938 Pass
Location : Fill placement at roadway between B6.2 ST G1, B6 ST JB and B4-ST JB, Elv/Depth :6 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, August 26, 2026
Reviewer Name / DateKenneth Mosman, September 01, 2026