- Density Test Report Report ID: 97505
- Edit Download Report
Density Test Report
Date :09/08/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :09/08/2026 07:30
Onsite Hours :10:00
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :sunny
Departure Time :09/08/2026 17:30
ASEC Technician Name :Clyde Smith
Observations/Finding
| Test Date | Test Number | Moisture Content (%) | Dry Density (pcf) | Proctor Number | Max. Dry Density (pcf) | Optimum Moisture (%) | Compaction (%) | Specified Compaction (%) | ASTM Test Method | Pass/Fail |
|---|---|---|---|---|---|---|---|---|---|---|
| 09/08/2026 | 1 | 13.6 | 99.6 | 2025-033 SP | 104.0 | 16.2 | 95.8 | 95 | D6938 | Pass |
| Location : | Backfill at west side abutment wall to sanitary sewer manhole #2 , Elv/Depth :4 feet below final grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 09/08/2026 | 2 | 13.2 | 99.6 | 2025-033 SP | 104.0 | 16.2 | 95.8 | 95 | D6938 | Pass |
| Location : | Same as 1, Elv/Depth :4 feet below final grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 09/08/2026 | 3 | 14.0 | 100.1 | 2025-033 SP | 104.0 | 16.2 | 96.2 | 95 | D6938 | Pass |
| Location : | Same as 1, Elv/Depth :2 feet below final grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
| 09/08/2026 | 4 | 22.4 | 92.0 | 2025-032 SP | 94.9 | 25.0 | 96.9 | 95 | D6938 | Pass |
| Location : | Same as 1, Elv/Depth :2 feet below final grade | |||||||||
| Comment : | Gauge Serial No. :91643 | |||||||||
Technician Signature / DateClyde Smith, September 8, 2026
Reviewer Name / DateKenneth Mosman, September 09, 2026