Density Test Report

Date :09/23/2026
Project No :2026C100
Client Company :Artisan
Arrival Time :09/23/2026 07:30
Onsite Hours :10:00
Name of the Project :Naturewalk PHASE 3, UNIT 4 (formerly called PH 2 Extension) Lots
Project Location :Dallas
Weather :Sunny
Departure Time :09/23/2026 17:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/23/2026 1 13.1 99.6 2025-033 SP 104.0 16.2 95.8 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 2 14.2 100.6 2025-033 SP 104.0 16.2 96.7 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 3 14.0 101.0 2025-033 SP 104.0 16.2 97.1 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 4 12.2 105.3 2025-035 SP 107.8 13.0 97.7 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 5 13.3 105.8 2025-035 SP 107.8 13.0 98.1 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 6 21.6 90.8 2025-032 SP 94.9 25.0 95.7 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
09/23/2026 7 22.1 112.8 2025-032 SP 94.9 25.0 97.4 95 D6938 Pass
Location : Unit 4, Phase 3 lots, Elv/Depth :Approximately 8 feet below grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, September 23, 2026
Reviewer Name / DateKenneth Mosman, October 21, 2026