Daily Field Report

Date :09/25/2026
Project No :2025C215
Client Company :Artisan
Arrival Time :09/25/2026 07:30
Onsite Hours :9:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :09/25/2026 16:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative observed subgrade preparation and proof-rolling of subgrade soils for the west side of bridge between the bridge and roundabout. The subgrade was proof-rolled using a loaded tandem dump truck. The subgrade soils appeared stable under traffic and was approved for base stone placement. The paving contractor began placing base stone over the subgrade and continued fine grading and compacting for the east side of the bridge.

The grading contractor Thompson continued subgrade preparation and backfilling behind curbing at Unit 4 phase 2.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Backfilling behind curbing and subgrade prep. at Unit 4 phase 2 by the Grading contractor

Subgrade prep.at Nature Walk Pkwy. to round about

Proof rolling of subgrade to round about

Technician Signature / DateClyde Smith, September 25, 2026
Reviewer Name / DateKenneth Mosman, October 21, 2026