Density Test Report

Date :09/29/2026
Project No :2026C100
Client Company :Artisan
Arrival Time :09/29/2026 07:30
Onsite Hours :10:00
Name of the Project :Naturewalk PHASE 3, UNIT 4 (formerly called PH 2 Extension) Lots
Project Location :Dallas
Weather :Sunny
Departure Time :09/29/2026 17:30
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
09/29/2026 1 13.4 103.4 2025-033 SP 104.0 16.2 99.4 95 D6938 Pass
Location : Building lots at Unit 4, Phase 3, Elv/Depth :4 feet below finished grade
Comment : Gauge Serial No. :91643
09/29/2026 2 14.1 101.8 2025-033 SP 104.0 16.2 97.9 95 D6938 Pass
Location : Building lots at Unit 4, Phase 3, Elv/Depth :3.5 feet below finished grade
Comment : Gauge Serial No. :91643
09/29/2026 3 14.2 102.9 2025-033 SP 104.0 16.2 98.9 95 D6938 Pass
Location : Building lots at Unit 4, Phase 3, Elv/Depth :3.5 feet below finished grade
Comment : Gauge Serial No. :91643
09/29/2026 4 12.6 106.7 2025-035 SP 107.8 13.0 99.0 95 D6938 Pass
Location : Building lots at Unit 4, Phase 3, Elv/Depth :3.5 feet below finished grade
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, September 29, 2026
Reviewer Name / DateKenneth Mosman, October 21, 2026