Density Test Report

Date :11/17/2026
Project No :2026C100
Client Company :Artisan
Arrival Time :11/17/2026 07:30
Onsite Hours :9:30
Name of the Project :Naturewalk PHASE 3, UNIT 4 (formerly called PH 2 Extension) Lots
Project Location :Dallas
Weather :sunny
Departure Time :11/17/2026 17:00
ASEC Technician Name :Clyde Smith

Observations/Finding

Test Date Test Number Moisture Content (%) Dry Density (pcf) Proctor Number Max. Dry Density (pcf) Optimum Moisture (%) Compaction (%) Specified Compaction (%) ASTM Test Method Pass/Fail
11/17/2026 1 13.7 103.1 2025-035 SP 107.8 13.0 95.6 95 D6938 Pass
Location : Backfill @ 8" pvc sanitary sewer line between Z 11.10 and Z 11.11, Elv/Depth :-4'
Comment : Gauge Serial No. :91643
11/17/2026 2 11.8 104.6 2025-035 SP 107.8 13.0 97.0 95 D6938 Pass
Location : Same as 1, Elv/Depth :-4'
Comment : Gauge Serial No. :91643
11/17/2026 3 14.2 114.1 2025-033 SP 104.0 16.2 96.1 95 D6938 Pass
Location : Same as 1, Elv/Depth :-2'
Comment : Gauge Serial No. :91643
11/17/2026 4 14.3 101.7 2025-033 SP 104.0 16.2 97.8 95 D6938 Pass
Location : Same as 1, Elv/Depth :-2'
Comment : Gauge Serial No. :91643
Technician Signature / DateClyde Smith, November 17, 2026