Skip to content

Daily Field Report

Date :01/15/2025
Project No :2024C202
Client Company :CCG
Arrival Time : 07:30
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Clear sky
Departure Time :01/15/2025 15:30
ASEC Technician Name :Solomon Cherie

Observations/Finding

The down cutting ad backfill a activity was done for a while, but stopped due to high mixture content and allow compaction. Nuclear gauge test shows 32% moisture and way belolow 95% compaction. As a result tilling and scarification was proposed and backfill is stopped for a while.

  • After scarification, the dirt was spread and packed.

Then another backfill was done for the road way. Another dirt was dug a and was i n good moisture and high compaction of 99% was observed.

Scarfied to drop the moisture and repack

Technician Signature / DateSolomon Cherie, January 15, 2025
Reviewer Name / DateKenneth Mosman, January 17, 2025