Daily Field Report
Date :04/03/2025
Project No :2024C202
Client Company :CCG
Arrival Time :04/03/2025 07:30
Onsite Hours :
Name of the Project :Old Griffin Rd - Hawthorne Reserve
Project Location :Dallas
Weather :Sunny
Departure Time :04/03/2025
ASEC Technician Name :Solomon Cherie
Observations/Finding
The downcutt and backfilling activities were carried out as usual for the day. The downcutt is in a close by cut area and is done by the 349E CAT Excavator. The two heat duity 745C Loading Truck did hauling of first from cut area to the backfill area.
The back fill location is at Lots# 48 & 49. The 61Pxi Komatsu Bulldozer spread the hauled dirt whereas the 815F sheet foot CAT Roller compacted the dirt.
Nuclear gauge test shows 95% compaction and slightly higher moisture to the optimum. However, proof rolling shows no pumping suggesting good compaction.
The total area of backfill for the day is 160×100 square feet.
Technician Signature / DateSolomon Cherie, April 3, 2025
Reviewer Name / DateKenneth Mosman, May 01, 2025