Daily Field Report

Date :12/11/2025
Project No :2025C260
Client Company :Artisan
Arrival Time :12/11/2025 11:30
Onsite Hours :04:00
Name of the Project :NW (PHASE 2) Parkway Extension
Project Location :Dallas
Weather :Sunny
Departure Time :12/11/2025 15:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

Our representative was on site to observe the grading contractor continue placing rock fill for th slope embankment in compacted lifts using a dozer to spread and a sheep-foot vibratory roller for compacting. The fill was placed in accordance with recommendations and appeared suitably compacted as per job specifications.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Undercutting rock fill from Nature Walk Parkway near sanitary sewer manhole #9

Fill placement at slope embankment

Wet conditions at haul road to slope embankment

Fill placement at slope embankment

Technician Signature / DateClyde Smith, December 11, 2025
Reviewer Name / DateKenneth Mosman, January 29, 2026