Daily Field Report

Date :02/05/2026
Project No :2025C215
Client Company :Artisan
Arrival Time :02/05/2026 08:00
Onsite Hours :9:30
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :cloudy
Departure Time :02/05/2026 17:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was on site to observe the pipe contractor (Savannah) continue installing 8″ ductile iron sanitary sewer line between manhole s#15 and 16 and backfilling using rock fill and soil between manholes # 13 and 16. The backfill was observed and tested in accordance with job specifications of rock fill and soil materials. Observations and testing was found to meet job specifications. The pipe contractor also began to install 48″ RCP storm line for the detention pond for the Unit 4 phase 2 OCS structure by setting the headwall structure. The writer probed the in-place fill at locations for the headwall and found them to be loose and not sufficiently compacted. The contractor was referred to recommendations made in our report dated 1/20/26 to replace core backfill around the pipe with a clay-based soil material replacing the lightweight sandy silt. The installation was cancelled today to make plans for replacement tomorrow. The water pipeline contractor also continued installing 8″ ductile iron water line at Unit 4 phase 1A between building Lots #22 and 18 for a total of 280 linear feet and installing a fire hydrant at Lots #22 and 21.

The grading contractor also continued placing fill for building Lots #56 thru 59.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

1Backfill between manhole # 13 and 14 and compacting

Backfill between Manhole #15 and 16

Density tests performed between manhole #13 thru 15

8" ductile iron water line installation between Lots #22 and 18

Sub grade observations at OCS headwall structure

Fill placement at Lots # 56 thru 59

Technician Signature / DateClyde Smith, February 5, 2026
Reviewer Name / DateKenneth Mosman, February 16, 2026