Daily Field Report

Date :07/10/2026
Project No :2025C215
Client Company :Artisan
Arrival Time :07/10/2026 07:30
Onsite Hours :08:00
Name of the Project :NW Unit 4 Parkway Ext. Phase 1
Project Location :Dallas
Weather :Sunny
Departure Time :07/10/2026 15:30
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was onsite to observe the paving contractor continue to place base stone over the existing subgrade soils at Naturewalk Parkway between sanitary sewer manholes #12 and 14. The writer continued to observe additional traffic from subcontractors which caused additional repairs being needed on subgrade prior to placing subbase stone.

The grading contractor continued placing fill for unit 4 phase 3 which was observed and tested by another technician from ASEC.

The wall contractor continued to place reinforcing steel at the bridge floor slab.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Placing sub base stone and compacting

Additional sub contractors traffic on sub grade causing additional repairs needed.

Technician Signature / DateClyde Smith, July 10, 2026
Reviewer Name / DateKenneth Mosman, July 30, 2026