Daily Field Report

Date :07/16/2026
Project No :2025C214
Client Company :Artisan
Arrival Time :07/16/2026 09:00
Onsite Hours :04:00
Name of the Project :NW Unit 4 BRIDGE (Materials Testing)
Project Location :Dallas
Weather :cloudy
Departure Time :07/16/2026 13:00
ASEC Technician Name :Clyde Smith

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services.  Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the above date our representative was onsite to observe the wall contractor (RWS) continuing to install reinforcing steel for the bridge panels. The contractor also completed form work for the wall pour at the dead man footing.

Our representative observed site conditions at Seven Hills phase 13.  Several areas had severe saturated eroded conditions.

Observed the pipe contractor (Savannah) continue installing 18″ storm line between structures Y2 and Y3.

Observed the eroded subbase conditions at Naturewalk parkway between sanitary sewer manholes #12 and 13 requiring repairs at the curb lines.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

 

Eroded sub base stone at Nature Walk curb line between sanitary sewer manholes #12 and 13

Saturated sub grade conditions at Nature Walk Pkwy.

Severe erosion conditions at Seven Hills phase 13

Continuing reinforcing steel installation at bridge panels and barrier walls

Technician Signature / DateClyde Smith, July 16, 2026
Reviewer Name / DateKenneth Mosman, July 30, 2026