- Home
- Daily Field Report Report ID: 96312
- Edit Download Report
Daily Field Report
Observations/Finding
On the above date the writer was on site as requested and assisted in monitoring and testing concrete pour for bridge slab deck pour of 135 yards.The writer assisted in molding three sets (6) 4×8 cylinders,see additional report dated today by ASEC technician.
The writer reobserved placement of reinforcing steel at bridge panels prior to concrete pour.Discrepancies observed on 7/17/26 were corrected.
The writer also observed proof rolling of remaining damaged sub grade to sanitary sewer manhole #12 using a loaded tandem dump truck having 18 plus tons.The sub grade was also observed by members from NWGP who begin repair measures clipping damaged sub grade to replace with additional base stone.The contractor clipped out a section today recommended for 4″ placing six loads of base stone with contract base stone included.
The writer also observed the Grading contractor hammering residual rock at building lots.

Reinforcing steel in place at panels deck


Resteel observations panel decks were cleaned

Sampling of placed concrete

Concrete placement at sidewalk

Concrete placement by pumping

#6 vertical bars in place at support dowel rods

Observing proof of remaining subgrade to sanitary sewer manhole # 12 which clipping was recommended to repair from rain events and construction traffic





Hammering of residual rock at bldg lot
