- Home
- Daily Field Report Report ID: 97418
- Edit Download Report
Daily Field Report
Date :09/03/2026
Project No :Admin
Client Company :ASEC
Arrival Time :09/03/2026 09:00
Onsite Hours :02:30
Name of the Project :Administrative - Non Billable
Project Location :
Weather :Sunny
Departure Time :09/03/2026 11:30
ASEC Technician Name :Clyde Smith
Observations/Finding
On the above date the writer was on site as requested at 145 Rosemary Landing project #887082 for inspection at footings/slab.The footings were observed by probing the bottoms using a rounded end steel rod at intervals of two to three feet.The in place fill and residual soils appeared suitable for a design bearing pressure of 3000 psf,The writer also observed reinforcing at continuous wall footings and floor slab reinforcing (2 # 4 continuous bars in place at all required locations.Lot number ,1074 NatureWalk @Seven Hills

Continuous exterior wall footings

Floor slab footings


Continuous reinforcing steel in place

Building permit

Probing bottom of footings

Technician Signature / DateClyde Smith, September 3, 2026
Reviewer Name / DateKenneth Mosman, September 08, 2026