Daily Field Report

Date :05/22/2023
Project No :2023C111
Client Company :2MATL
Arrival Time :05/22/2023 22:00
Onsite Hours :08:30
Name of the Project :DOA Fiber Infrastructure Improvements
Project Location :HJAIA
Weather :overcast
Departure Time :05/23/2023 06:30
ASEC Technician Name :Isaac Davis

Observations/Finding

As requested, our ASEC representative was on site to observe daily activities.  The following was observed this day:

Density testing for DOA Fiber AVS NS.

Location: DOA Fiber AVS NS (North of Economy Parking Exit)

Objective: The objective of this report is to provide a summary of the density test conducted at the DOA Fiber AVS NS site. The density test was carried out by Isaac Davis an ASEC technician to assess the compaction and moisture levels of various lifts within the project area.

Procedure:

  1. ASEC technician Isaac Davis arrived on site at DOA Fiber AVS NS.
  2. BBH contractors completed conduit installation, tying it into the manhole.
  3. Density test readings were taken for each lift as described below:

Test Results:

Lift #1:

  • Initial Test Reading:
    • Wet Density: 118.8 pcf
    • Dry Density: 112.8 pcf
    • Moisture Content: 5.4%
    • Compaction: 91%
  • Retest Reading:
    • Wet Density: 121.0 pcf
    • Dry Density: 111.6 pcf
    • Moisture Content: 8.4%
    • Compaction: 90%

Lift #2:

  • Wet Density: 125.7 pcf
  • Dry Density: 112.9 pcf
  • Moisture Content: 11.4%
  • Compaction: 91%

Lift #3:

  • Wet Density: 127.0 pcf
  • Dry Density: 115.1 pcf
  • Moisture Content: 10.3%
  • Compaction: 92.8%

Lift #4:

  • First Test Reading:
    • Wet Density: 115.4 pcf
    • Dry Density: 106.8 pcf
    • Moisture Content: 8.0%
    • Compaction: 86.5%
  • Retest Reading:
    • Wet Density: 121.9 pcf
    • Dry Density: 112.5 pcf
    • Moisture Content: 8.4%
    • Compaction: 90.7%

Lift #5:

  • Wet Density: 122.9 pcf
  • Dry Density: 114.1 pcf
  • Moisture Content: 7.7%
  • Compaction: 92%

Lift #6:

  • Wet Density: 127.9 pcf
  • Dry Density: 115.1 pcf
  • Moisture Content: 11.0%
  • Compaction: 92.8%

Upon completion of density testing, it was observed that the measured values for all lifts were within the specified limits, indicating satisfactory compaction and moisture levels. The project area at DOA Fiber AVS NS met the required specifications based on the test results.

 

Technician Signature / DateIsaac Davis, May 22, 2023
Reviewer Name / DateKenneth Mosman, July 08, 2023