Daily Field Report
Observations/Finding
Our AS Engineering & Consulting (ASEC) representative arrived on site to observe field activities. The following tasks were performed:
The contractor’s plan for today was continue filling the backside of Lots #27 through #31. However, the superintendent changed the plan and proceeded with topsoil hauling.
Storm lines between Manholes E2 and E1 were backfilled and compacted. General probing using a 3/8″ diameter probe rod showed this area to be stable.
Sewer lines between Manholes E2 and E3 was planned to be backfilled but was not completed today.
Please contact us if you have any questions regarding this report or of the density test results.

Picture depicting top soil hauling and filling on the green are behind the lots

Picture showing storm line stretched between Manholes E2/and E1