Observations/Finding
As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.
Our representative was on site to observe the grading contractor continue placing rock fill for th slope embankment in compacted lifts using a dozer to spread and a sheep-foot vibratory roller for compacting. The fill was placed in accordance with recommendations and appeared suitably compacted as per job specifications.
We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Undercutting rock fill from Nature Walk Parkway near sanitary sewer manhole #9


Fill placement at slope embankment

Wet conditions at haul road to slope embankment

Fill placement at slope embankment