Daily Field Report

Date :12/16/2025
Project No :2025C269
Client Company :Lewis Contracting
Arrival Time :12/16/2025 08:00
Onsite Hours :9:00
Name of the Project :Main St. & First Ave. - Mixed-use
Project Location :Lilburn
Weather :sunny
Departure Time :12/16/2025 17:00
ASEC Technician Name :Samara Simha Reddy Kandi

Observations/Finding

As requested, the site was visited by our AS Engineering and Consulting (ASEC) representative for the purpose of providing quality control inspection and testing services. Visual observation techniques were employed to verify compliance with project drawing/specifications, applicable codes, and materials submittals. The following observations were observed on site this day.

On the next working day, construction activities continued at Pond 1, non-woven geotextile fabric was placed along the bottom and sides of the excavation, following fabric placement, a gravel bedding layer was installed and leveled.

The crew then installed corrugated metal pipes (CMP) in alignment with the existing detention system. Pipe installation at Pond 1 progressed to an approximate total length of 140 lineal feet. After installation, gravel was placed around and between the pipes. The open ends of the detention pipes were closed and wrapped with geotextile fabric to prevent soil intrusion and to protect the system prior to final backfilling.

At Pond 3, work focused on backfilling operations following completion of the detention system. Suitable fill material was placed around the pipes in controlled lifts of approximately 6 to 8 inches. Each lift was compacted using a sheep-foot roller, and backfilling continued to an approximate height of 3 feet on sides of the pipe system. Compaction was observed to be uniform, and the fill was compacted thoroughly to achieve the required density.

At Pond 2, backfilling activities were initiated. Fill material was placed to an approximate height of 1 foot in a single lift and compacted. However, compaction did not meet the required density, and the area failed compaction requirements. As a result, backfilling operations at Pond 2 were temporarily stopped pending corrective measures.

Following pond-related activities, the crew shifted operations at foundation wall to sd2-p 912. Fill material was placed to restore grades and compacted in two controlled lifts, each approximately 6 to 8 inches thick. Compaction was performed using compaction equipment, and the area was graded.

We appreciate the opportunity to be of service to you on this project. If you have any questions regarding this report, please feel free to contact us. We will be more than happy to discuss it with you.

Technician Signature / DateSamara Simha Reddy Kandi, December 16, 2025
Reviewer Name / DateKenneth Mosman, January 30, 2026